Projects Progress as at 10/05/2019
Ministry of Internal & Home Affairs and Provincial Councils & Local Government
No. | Location (Divisional Secretariat) | Project Name | Start Date |
Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/Design & Build | Consultant | Client |
Completion Date |
Physical Progress (%) |
Remarks |
|
31.01.2019 | 30.04.2019 | |||||||||||
01 | Mawathagama | Construction of office building Mawathagama Div.Sec. | 23.10.2017 | 77,816,632.01 | 61,515,124.12 | Sooriya Constructions | District Secretariat, Kurunegala | - | 31.03.2019 | 85 | 98 | Extra work to be done |
Ministry of Tourism Development, Wild Life and Christian Religious Affairs
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/Design & Build | Consultant | Client | Completion Date | Physical Progress (%) |
Remarks | |
31.01.2019 |
30.04.2019 | |||||||||||
02 | Udubaddawa | Constructions of proposed Rest house at Kattimahana St. Anne's Church | 10.10.2018 | 22,355,603.64 | 15,296,880.60 | M.R.T Contractors | District Secretariat, Kurunegala | - | 10.04.2019 | 70 | 82 | - |
Ministery of Telecommunication, Foreign Employment and Sports
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) |
Remarks | |
31.01.2019 |
30.04.2019 | |||||||||||
03 | Kurunegala | Project Construction of Proposed fire and Archery Range at Maliyadewa Boys College Kurunegala - stage 01 | 26.04.2018 | 14,310,060.06 | 12,230,760.79 | Jayasinghe Contractors | District Secretariat, Kurunegala | - | 23.05.2019 | 20 | 20 | Temporary suspended works due to non payment |
Projects Progress as at 10/02/2019
Ministry of Internal & Home Affairs and Provincial Councils & Local Government
No. | Location (Divisional Secretariat) | Project Name | Start Date |
Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/Design & Build | Consultant | Client |
Completion Date |
Physical Progress (%) |
Remarks |
|
31.12..2018 | 31.01.2019 | |||||||||||
01 | Mawathagama | Construction of office building Mawathagama Div.Sec. | 23.10.2017 | 77,816,632.01 | 61,515,124.12 | Sooriya Constructions | District Secretariat, Kurunegala | - | 31.03.2019 | 75 | 85 | - |
Ministry of Tourism Development, Wild Life and Christian Religious Affairs
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/Design & Build | Consultant | Client | Completion Date | Physical Progress (%) |
Remarks | |
31.12..2018 | 31.01.2019 | |||||||||||
02 | Udubaddawa | Constructions of proposed Rest house at Kattimahana St. Anne's Church | 10.10.2018 | 22,355,603.64 | 15,296,880.60 | M.R.T Contractors | District Secretariat, Kurunegala | - | 10.04.2019 | 70 | 75 | - |
Ministery of Telecommunication, Foreign Employment and Sports
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress | Remarks | |
31.12..2018 | 31.01.2019 | |||||||||||
03 | Kurunegala | Project Construction of Proposed fire and Archery Range at Maliyadewa Boys College Kurunegala - stage 01 | 26.04.2018 | 14,310,060.06 | 12,230,760.79 | Jayasinghe Contractors | District Secretariat, Kurunegala | - | 23.05.2019 | 20 | 20 | - |
Ministery of National Policies, Economic Affaris, Resettlement & Rehabilitation, Northern Provision Development, Vocational Training & Skills Development and Youth Affairs
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress | Remarks | |
31.12..2018 | 31.01.2019 | |||||||||||
04 | Mawathagama | Improvements of Kahapathwala Iriminna Road (0.480-2.000 km) | 10.10.2018 | 47,826,000.00 | 44,535,426.42 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 80 | 99 | * |
05 | Mawathagama | Improvements of Kahapathwala Iriminna Road (2.000-3.350 km) | 10.10.2018 | 38,114,000.00 | 35,452,728.79 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 80 | 99 | * |
06 | Kotawehera | Improvements ofIhalagama Junction - Nikawewa Road (Stage 01) | 17.10.2018 | 50,000,000.00 | 48,145,291.21 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 80 | 95 | * |
07 | Kotawehera | Improvements of Ihalagama Junction - Nikawewa Road (Stage 02) | 17.10.2018 | 50,000,000.00 | 48,145,291.21 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 80 | 95 | * |
08 | Kotawehera | Improvements of Ihalagama Junction - Nikawewa Road (Stage 03) | 30.10.2018 | 50,000,000.00 | 47,977,518.21 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 80 | 99 | * |
09 | Rideegama | Improvements of Rideevihara access Road Road (Stage 01) | 30.10.2018 | 68,868,691.46 | 6,421,052.00 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 99 | 99 | * |
10 | Rideegama | Improvements of Rideevihara access Road Road (Stage 02) | 30.10.2018 | 25,000,000.00 | 23,461,918.20 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 99 | 99 | * |
11 | Rideegama | Improvements of Rideevihara access Road Road (Stage 03) | 30.10.2018 | 25,000,000.00 | 24,093,596.68 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 99 | 99 | * |
12 | Nikaweratiya | Improvements of Nikaweratiya Police Station Meda Ela Ibbawala Road | 11.05.2018 | 35,315,000.00 | 34,076,657.59 | PRDD | District Secretariat, Kurunegala | - | 31.12.2018 | 80 | 90 | * |
* Funds Requested for Remaining Work
Photo Gallery
03. Minister of Telecommunication, Foreign Employment and Sports
I. Project Construction of Proposed fire and Archery Range at Maliyadewa Boys College Kurunegala - stage 01
04. Minister of National Policies, Economic Affaris, Resettlement & Rehabilitation, Northern Provision Development, Vocational Training & Skills Development and Youth Affairs as at 31.12.2018
I. Improvements of Kahapathwala Iriminna Road (0.480-2.000 km)
![]() |
![]() |
II. Improvements of Kahapathwala Iriminna Road (2.000-3.350 km)
![]() |
![]() |
![]() |
III. Improvements of Ihalagama Junction - Nikawewa Road (Stage 01)
IV. Improvements of Ihalagama Junction - Nikawewa Road (Stage 02)
V. Improvements of Ihalagama Junction - Nikawewa Road (Stage 03)
VI. Improvements of Rideevihara access Road Road (Stage 01)
![]() |
![]() |
VII. Improvements of Rideevihara access Road Road (Stage 02)
![]() |
![]() |
VIII. Improvements of Rideevihara access Road Road (Stage 03)
![]() |
![]() |
![]() |
IX. Improvements of Nikaweratiya Police Station Meda Ela Ibbawala Road