Project Progress as at 10/05/2019
Minister of Telecommunication, Foreign Employment and Sports
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) | Remarks |
30.04.2019 | |||||||||||
01 | Bingiriya | Construction of New Pavilion in L.B. Jayasena Ground Bingiriya | 09.10.2018 | 7,940,374.50 | 5,643,852.09 | W.P.J.Q Botheju, Gov. Contractor and supplier | District Secretariat, Kurunegala | - | 09.02.2019 | 48 | - |
02 | Panduwasnuwara East | Construction of New Pavilion in Kolambagama School Panduwasnuwara | 20.09.2018 | 7,940,374.50 | 5,388,261.97 | Jayamaha Construction | District Secretariat, Kurunegala | - | 20.01.2019 | 85 | - |
Minister of Megapolis & Western Development
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) | Remarks |
30.04.2019 | |||||||||||
03 | Ibbgamuwa | Construction of Multipurpose Buillding at Ayesha waththa, Yakalla | 02.10.2018 | 3,802,864.26 | 2,465,890.00 | SDS Sathurusinghe Construction | District Secretariat, Kurunegala | - | 02.01.2019 | 55 | - |
Ministry of Women & Child Affairs and Dry Zone Development
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) | Remarks |
30.04.2019 | |||||||||||
04 | Kuliyapitiya | Construction of Child & Women's development affairs bureau at Police Station Kuliyapitiya | 06.09.2018 | 6,019,279.84 | 4,974,006.30 | Dinidun Construction | District Secretariat, Kurunegala | - | 25.12.2018 | 90 | - |
Ministry of Buddhasasana & Wayamba Development
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) | Remarks |
30.04.2019 | |||||||||||
05 | Kurunegala | Concreting Road from Exsisting Samagi Uyana Concreted to Mangala Sooriya Bandara's Residence | 04.12.2018 | 2,755,712.97 | 2,332,729.60 | Dissanayaka Construction & Transport | District Secretariat, Kurunegala | - | 04.01.2019 | 45 | * |
06 | Bingiriya | Improvement the Talgahapitiya Jubily Mawatha (From Mr. Jayasumana's residence up to Mr.S.H Sunil Hewage's residence) | 17.12.2018 | 2,541,120.28 | 2,282,929.00 | Lankathilaka Construction | District Secretariat, Kurunegala | - | 31.12.2018 | 15 | - |
* Funds Requested for Remaining Work
Project Progress as at 10/01/2019
Minister of Telecommunication, Foreign Employment and Sports
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) |
Remarks | |
31.12.2018 | 31.01.2019 | |||||||||||
01 | Bingiriya | Construction of New Pavilion in L.B. Jayasena Ground Bingiriya | 09.10.2018 | 7,940,374.5 | 5,643,852.09 | W.P.J.Q Botheju, Gov. Contractor and supplier | District Secretariat, Kurunegala | - | 09.02.2019 | 25 | 35 | * |
02 | Panduwasnuwara East | Construction of New Pavilion in Kolambagama School Panduwasnuwara | 20.09.2018 | 7,940,374.50 | 5,388,261.97 | Jayamaha Construction | District Secretariat, Kurunegala | - | 20.01.2018 | 55 | 65 | * |
* Funds Requested for Remaining Work
Minister of Megapolis & Western Development
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) |
Remarks | |
31.12.2018 | 31.01.2019 | |||||||||||
03 | Ibbgamuwa | Construction of Multipurpose Buillding at Ayesha waththa, Yakalla | 02.10.2018 | 3,802,864.26 | 2,465,890.00 | SDS Sathurusinghe Construction | District Secretariat, Kurunegala | - | 02.01.2019 | 50 | 50 | * |
* Funds Requested for Remaining Work
Ministry of Women & Child Affairs and Dry Zone Development
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) |
Remarks | |
31.12.2018 | 31.01.2019 | |||||||||||
04 | Kuliyapitiya | Construction of Child & Women's development affairs bureau at Police Station Kuliyapitiya | 06.09.2018 | 6,019,279.84 | 4,974,006.30 | Dinidun Construction | District Secretariat, Kurunegala | - | 31.12.2018 | 50 | 60 | * |
* Funds Requested for Remaining Work
Ministry of Buddhasasana & Wayamba Development
No. | Location (Divisional Secretariat) | Project Name | Start Date | Estimated Cost (Rs.) | Contract Amount (Rs.) | Contractor/ Design & Build | Consultant | Client | Completion Date | Physical Progress (%) |
Remarks | |
31.12.2018 | 31.01.2019 | |||||||||||
05 | Kurunegala | Concreting Road from Exsisting Samagi Uyana Concreted to Mangala Sooriya Bandara's Residence | 04.12.2018 | 2,755,712.97 | 2,332,729.60 | Dissanayaka Construction & Transport | District Secretariat, Kurunegala | - | 04.01.2019 | 45 | 45 | * |
06 | Bingiriya | Improvement the Talgahapitiya Jubily Mawatha (From Mr. Jayasumana's residence up to Mr.S.H Sunil Hewage's residence) | 17.12.2018 | 2,541,120.28 | 2,282,929.00 | Lankathilaka Construction | District Secretariat, Kurunegala | - | 31.12.2018 | 15 | 15 | * |
* Funds Requested for Remaining Work